Bryn Cefni Trade Units for RL Davies

Wall cladding nearly completed, installation of flashing and rainwater goods to be installed in next few weeks.

22.09.2020 – Bryn Cefni trade units, using 120mm Kingspan MR and RW panels to walls.

04.08.2020

Here we have the steel being erected on one of our new projects for RL Davies.

We are due to start on site in the next 3 weeks to install the Kingspan KS/1000 RW and MR Composite Cladding to the roof and walls.